State Route 900 trail connector hits bump

November 16, 2010

By Warren Kagarise

Unstable soil causes crews to dig deeper

Construction crews continue work on a trail connector at Interstate 90 and state Route 900. Crews had to dig a little deeper last month to find stable soil for concrete-and-steel piers. By Greg Farrar

The trail connector under construction at Interstate 90 and state Route 900 hit a bump in the road last month, as crews had to dig deeper to reach a sturdier soil layer to support a series of concrete-and-steel piers.

City engineers said the extra digging is not expected to delay the project. The connector — arranged along almost one-third of a mile from the state Route 900 boardwalk on the south side of the interstate to the Sammamish Trail on the north — should be completed in April.

Crews needed to find a solid surface to support the piers and had to dig 20 feet to 30 feet deeper than initially estimated to find a bearing layer. The snag prompted the Issaquah contractor C. A. Carey Corp. to bring in additional equipment to complete the digging.

“It’s still kind of a concern, but they’re continuing to work and we’re working through the issues between us and WSDOT and the contractor,” city Public Works Engineering Director Bob Brock said.

Plans call for the completed connector to feature a 12-foot-wide pedestrian bridge across the westbound interstate on-ramps, plus a 10-foot-wide pedestrian crossing on the existing state Route 900 overpass.

Brock said the contractor had to meet construction standards updated after the 2001 Nisqually earthquake.

“We’re building it to the most current standards, which is causing us to drill down further to get to a little extra bearing,” he said.

City Senior Engineer Rory Cameron said the construction slowdown lasted for about a week in October. The extra feet equaled extra dollars, but engineers said the project had reserve funds built into the budget.

The city awarded the $4.4 million construction contract to C. A. Carey Corp. in June. The total project price tag is about $6 million.

The project relies on grants — including $400,000 from Sound Transit — to offset most of the project cost. The city contributed about $341,000 toward the link. Construction on the project started in July.

Engineers said the project has not faced any serious problems so far and, aside from some traffic backups in the early days, construction has been smooth.

The contract narrowed driving lanes on state Route 900 and closed a high-occupancy vehicle lane to serve as a construction staging area.

In the initial phase, not enough drivers used the center lane on the state Route 900 overpass, causing construction-related traffic backups. The city encouraged drivers to use the center lane to prevent backups and adjusted traffic flow through the corridor.

Warren Kagarise: 392-6434, ext. 234, or wkagarise@isspress.com. Comment at www.issaquahpress.com.

Bookmark and Share
Other Stories of Interest: , , , , , , ,

Comments

One Response to “State Route 900 trail connector hits bump”

  1. Gabe on November 17th, 2010 11:01 am

    “In the initial phase, not enough drivers used the center lane on the state Route 900 overpass, causing construction-related traffic backups.”

    It does seem like NW drivers do tend to stack up in one lane only and don’t understand that you’re not allowing someone to cut in line when two lanes converge into one. Allowing merging is the correct and accepted method of driving elsewhere in the U.S.!

Got something to say?

Before you comment, please note:

  • These comments are moderated.
  • Comments should be relevant to the topic at hand and contribute to its discussion.
  • Personal attacks and/or excessive profanity will not be tolerated and such comments will not be approved.
  • This is not your personal chat room or forum, so please stay on topic.