Apollo, Issaquah Valley budgets revised

May 27, 2014

By Staff

The ongoing construction projects at Apollo and Issaquah Valley elementary schools had details revised for a third time at the Issaquah School Board’s May 14 meeting.

A revised contract of $10,318,949 was approved at the meeting, an increase of $141,622 from the previous amount. Babbit Neuman Construction Co. is the contractor on the two schools.

The revisions include changing storage rooms into small instructional spaces, sound-system changes in multipurpose classrooms, and the addition of call buttons in classrooms and activity spaces at both schools.

The revised contract total is within the board’s original budget.

Bookmark and Share
Other Stories of Interest: , , ,

Comments

Got something to say?

Before you comment, please note:

  • These comments are moderated.
  • Comments should be relevant to the topic at hand and contribute to its discussion.
  • Personal attacks and/or excessive profanity will not be tolerated and such comments will not be approved.
  • This is not your personal chat room or forum, so please stay on topic.