School district makes $70,000 in change orders

September 23, 2014

Nearly $70,000 in change orders have been made to the construction projects at Apollo and Issaquah Valley elementary schools.

A contract with Babbit Neuman Construction Co. has been increased by $68,661.32. The revised contract total of $12,165,180.02 is within the project budget.

The amount includes siding, combining two classrooms into a single large classroom and changing faucets in restrooms to automatic faucets.

Both schools held ribbon-cutting ceremonies earlier this month, commemorating the official end of modernization efforts that were approved by voters in 2012.

Issaquah school board approves changes to Liberty modernization plan

June 3, 2014

The Issaquah School Board approved a pair of change order requests regarding Liberty High School’s modernization project at its May 28 meeting.

The first change added more than $116,000 to a contract with Babbit Neuman Construction Co. More than 20 changes were needed to comply with various project specifications and building codes, including some railings, ductwork, fire extinguishers and sprinklers.

The second change added nearly $9,000 to a contract with construction firm Kassel & Associates. Four minor upgrades were approved, including the addition of fire-retardant plywood on a wall assembly, and vent piping for a sink.

The additional money being spent is within the budgets of both projects.

Apollo, Issaquah Valley budgets revised

May 27, 2014

The ongoing construction projects at Apollo and Issaquah Valley elementary schools had details revised for a third time at the Issaquah School Board’s May 14 meeting.

A revised contract of $10,318,949 was approved at the meeting, an increase of $141,622 from the previous amount. Babbit Neuman Construction Co. is the contractor on the two schools.

The revisions include changing storage rooms into small instructional spaces, sound-system changes in multipurpose classrooms, and the addition of call buttons in classrooms and activity spaces at both schools.

The revised contract total is within the board’s original budget.