Residents doubt flood-handling promises for Gilman

March 11, 2014

City and developer assurances couldn’t hold back a flood of doubt March 4.

The Rivers and Streams Board held a public hearing about plans for redevelopment on Seventh Avenue Northwest and Northwest Gilman Boulevard. Almost 40 people attended to hear how developer Lennar Multifamily Investors’ residential building plans might affect the existing floodplain.

“We’re primarily here to hear the public’s comments,” City Environmental Planner Peter Rosen said at the meeting. “There’s a lot of information and a lot of issues in terms of the building design, and that’s going to be dealt with by the development commission. Here, we’re trying to focus on the natural resource issues and flooding.”

Read more

Project leader: Issaquah Creek renovation almost complete… again

March 4, 2014

After nearly six months of delays, the Issaquah Creek dam replacement could be finished next month.

Originally slated to be done Sept. 15, the project to remove the 60-year-old dam and replace it with a sloping set of rock weirs experienced weather problems and some undefined setbacks.

State Fish and Wildlife Project Manager Tim Ward said the $3.1 million project is still within the established budget contingency. However, that could change before contractors finish the job.

“Essentially, the contractor incurred some extensions that we’re negotiating right now,” Ward said.

Read more