Hatchery to drive salmon upstream due to dam construction delay

August 27, 2013

By Greg Farrar Workmen with SNC-Lavalin place a temporary lateral brace lowered by crane Aug. 16 for permanent sheet pile walls, which will surround the new hatchery water intake structure at Issaquah Creek.

By Greg Farrar
Workmen with SNC-Lavalin place a temporary lateral brace lowered by crane Aug. 16 for permanent sheet pile walls, which will surround the new hatchery water intake structure at Issaquah Creek.

With the Issaquah Creek dam renovation falling behind schedule, trucks will take spawning salmon upstream.

For a number of reasons, some vague, the project completion date has been pushed back from Sept. 15 to sometime in early to mid-October. That will heavily interfere with the spawning run of returning chinook and coho salmon. As a contingency, Issaquah Salmon Hatchery workers will gather the fish, truck them to a point beyond the construction and return them to the creek.